Cont. of Earthen Dam & Allied Works across Dhavri River near Morbe. Dist. Raigad. 1998-1999
Construction Abhishek Cotspin Mills Ltd., At Tamgaon, Tal:- Karveer, Dist:- Kolhapur. 2001-2002
Excavation, Prehearing, Dewatering & Drilling, Anchor Bars & all type of other works for main plant
Building’s and Structures of Kaiga Atomic Power Project Units 3 & 4.
2002-2003
Construction of Approach Road to Contractors facility at Kaiga Village.2002-2003
Balance work Tail Chaneel of Waste Weir of Kumbhi Medium project.2005-2005
Civil Works of Rajivji Sahkari Soot Girni Ltd., Dindnerli, Dist.- Kolhapur. 2009-2010
Construction of Earthwork & Structures (with contractor’s own design and structures) in Km. No.1 of Link canal No.I & in Km.No. 6 of Link Canal II 2010-2011
Cont. of Balance Earthwork & Structures in Km. No.9,17,19,20,24 & in Km. No 26 to 45 of Khatav Canal (JV Work). 2010-2011
Construction of Earthwork and C.D. Work in Km. 33 to 38 and R.C.C. trough Aqueduct on R/B canal of Shivna Takali Medium Project. 2011-2012

Current Projects

Current Projects
Project DetailsStipulated Date of Completion
Construction of Earthen Dam & its appurtenant works across Ambeohol Nalla near Ardal, Tal.Ajara, Dist. Kolhapur.30-6-2016
Construction of M.I. Tank at Vagade, Tal. Kankavali, Dist.-Sindhudurg.30-6-2017
Strengthening the Canal in between Km. No. 1 to 5 of Dudhganga Right Bank Canal.30-6-2017
Construction of Eartwork & Structures of Km. No. 1 & 15 of Kolhapur Branch of Dudhganga Left Bank Canal.30-6-2018